410 Riverview Lane Storm Repair

Published on February 02, 2026

410 Riverview Ln Storm Repair project location

Storm sewer replacement of the failing stormwater pipe lateral across Riverview Lane which has resulted in the expanding hole in the roadway, will begin on February 9, 2026.

Road signs and maintenance of traffic will be established followed by excavation, lateral pipe removal/replacement, asphalt removal/replacement, grading, sodding/seeding, and associated work.

Work will start on the north side of the road, proceed to the south side, and be completed within 5 business days.

The road will continue to be open during construction, reducing to one lane as both sides are completed.

Atlantic Development of Cocoa, Inc., is the contractor of record.

For questions or additional information, please contact Town Hall at (321) 724-5860 or visit our Projects in Action page for updates.